Ground-up construction loans: how lenders size them for developers
- Section
- AvenStead Academy, loan types
- Written by
- Angelo Orru Neto, MSc, CFP®. AvenStead Capital
- Updated
Key points
- A ground-up construction loan is sized on your total project cost (loan-to-cost) and capped by what the finished building is expected to be worth (loan-to-completed-value), whichever gives the smaller loan.
- Many lenders in the small-developer space commonly lend somewhere between 60% and 85% of total cost, so you should expect to bring 15% to 40% of the budget as equity, often including the land.
- The money is not handed over at closing: it is released in draws after an inspector confirms the work, and you usually pay interest only on what has been drawn.
- Lenders look hard at your experience, your general contractor and a complete budget with a contingency, because a half-built building is difficult collateral.
- Know your exit before you start: either a construction-to-permanent loan that converts after completion, or a separate take-out loan or a sale that pays the construction loan off.
A ground-up construction loan pays for a new building that does not exist yet. Because the collateral is a plan, a budget and a piece of land, lenders size the loan on what the project costs and what it should be worth when finished, release the money only as work is done, and look closely at whether you can finish. This guide walks through each of those pieces the way a lender reads them.
How lenders size a ground-up construction loan
Two numbers set the loan, and the lender uses whichever gives the smaller amount.
The first is loan-to-cost (LTC): the loan divided by the total project cost. Total cost means everything: land, hard costs (site work, materials and labor), soft costs (design, permits, insurance, fees), a contingency and the interest you will pay during construction. Many lenders that work with small developers commonly lend somewhere between 60% and 85% of total cost. Banks tend to sit at the lower end; many private lenders go higher in exchange for a higher rate.
The second is loan-to-completed-value, sometimes called loan-to-ARV (after-repair or as-completed value). An appraiser estimates what the finished building will be worth, and the lender caps the loan at a share of that, commonly in the 60% to 75% range.
For more on these ratios, see LTV, LTC and ARV explained.
Illustrative example: a developer plans four townhomes.
| Line | Amount |
|---|---|
| Land (owned, counted at cost) | $400,000 |
| Hard costs | $1,200,000 |
| Soft costs | $200,000 |
| Contingency (5% of hard costs) | $60,000 |
| Interest reserve | $90,000 |
| Total project cost | $1,950,000 |
At 75% loan-to-cost, the loan would be $1,950,000 × 0.75 = $1,462,500. The appraiser puts the completed value at $2,400,000, and the lender caps the loan at 65% of that: $2,400,000 × 0.65 = $1,560,000. The smaller number wins, so the loan is $1,462,500 and the developer’s equity is $1,950,000 − $1,462,500 = $487,500. Since the land counts for $400,000 of that, the developer brings $87,500 more in cash, before closing costs.
What a lender wants to see in your budget
The budget is the document a construction lender reads most closely. A credible one usually includes:
- A line-item hard cost budget from your general contractor (GC), often with a signed construction contract.
- Soft costs listed separately, including permits, impact fees, architecture, engineering and builder’s risk insurance.
- A contingency, commonly 5% to 10% of hard costs, for the surprises every build has.
- Plans and permits, or a clear path to them. Many lenders will not close until permits are issued or ready to issue.
Lenders often hire a third-party reviewer to check that your budget and schedule are realistic for the plans. If the reviewer thinks the budget is light, expect the lender to ask you to add to the contingency or bring more equity.
How draws and inspections work
You do not receive the construction loan as one payment. The lender holds it and releases it in draws, usually monthly or at set milestones such as foundation, framing, dry-in and finishes.
A typical draw goes like this:
- You or your GC submit a draw request listing the work completed and the invoices.
- An inspector visits the site and confirms the work is in place.
- The lender often checks for lien waivers from the GC and major subcontractors, so no one can later claim against the property for unpaid work.
- The lender releases the amount the inspector confirmed, often less a retainage (a share held back until the end).
Many lenders require your equity to go in first, so the first draws come from your money and the lender’s money follows. Interest is usually charged only on the amount drawn so far, not on the full loan. Plan for the gap between when your GC wants paying and when a draw arrives: a week or two is common.
What an interest reserve is and why lenders want one
An interest reserve is a line in the budget, paid from the loan, that covers the monthly interest during construction. The building earns no rent while it is being built, so the reserve keeps the loan current without you writing a check each month.
Lenders size the reserve on the expected draw schedule. Because the balance grows as the work progresses, the interest grows too, so the reserve is usually much less than a full year of interest on the whole loan. If the build runs late, the reserve can run out, and the interest then comes from your pocket. That is one reason a realistic schedule matters as much as a realistic budget.
What experience construction lenders expect
A half-built building is hard to sell and hard to finish for someone else, so lenders ask, in effect, “Will this person finish?” They commonly look at:
- Your track record: completed projects of a similar type and size, with addresses, costs and outcomes.
- Your GC: licensed, insured, bonded where required, with a record of similar work.
- Your liquidity: cash beyond your equity, so you can cover overruns.
- Your credit and net worth, because small construction loans are commonly full recourse (you sign personally) and often carry a completion guaranty.
A first project is not always a dead end. Lenders may still consider it with lower leverage, an experienced GC or a partner who has built before.
Construction-to-permanent or a separate take-out
Every construction loan needs a way to be paid off. There are two common paths.
Construction-to-permanent. One loan covers the build and then converts into a long-term loan once the building is finished and meets the lender’s conditions, such as a certificate of occupancy and, for income property, a minimum occupancy or debt service coverage. You close once, which saves a second set of closing costs and removes some refinance risk. The trade-off is that fewer lenders offer it, and the permanent terms are set before the building exists.
Take-out. The construction loan is short term, and you pay it off with a separate permanent loan or a sale. For income property, the take-out lender will size the new loan on the building’s actual rent, using measures like the debt service coverage ratio (see DSCR explained). If rents come in lower than planned or rates rise, the take-out loan may be smaller than the construction loan, and you would need to bring cash to close the gap. Some developers bridge that period with a bridge loan while the building leases up.
For a for-sale project, the exit is the sales of the units. Lenders will ask how many you expect to sell and how quickly, and many require a share of each sale to pay down the loan.
How AvenStead can help
The AvenStead screen asks the same questions construction lenders ask first: the budget, the land, the completed value and your experience. Once you send it, you see a green, yellow or red screen result, and an advisor follows up to introduce you to the lenders in our matrix whose programs fit. Read more on the construction loan page, or start the screen.
Questions owners ask
- Can I use the land I already own as my equity?
- Often, yes. Many lenders count land you own toward your share of the cost, commonly at what you paid for it or at its appraised value, depending on the lender and how long you have owned it. Any loan on the land is usually paid off at closing from the construction loan, which reduces how much equity the land is worth to you.
- What counts as a soft cost?
- Soft costs are the costs that are not bricks and labor: architecture and engineering, permits and impact fees, surveys, insurance, legal, the lender's fees and interest during construction. Lenders want them in the budget from the start, because a project that runs out of money for permits stalls as surely as one that runs out of lumber.
- Do I need experience to get a construction loan?
- Most lenders want to see that you, or a partner on the deal, have completed projects of a similar type and size. First-time developers are not always turned away, but they usually face lower leverage, a stronger general contractor requirement or a request for an experienced partner or guarantor.
- Is a construction loan recourse?
- Small construction loans are commonly full recourse, meaning you sign a personal guaranty for the loan. Lenders also often ask for a completion guaranty, a promise that you will finish the building even if costs run over. Read both with your lawyer before you sign.
- How long does a construction loan last?
- Terms commonly run 12 to 24 months for smaller projects, sometimes with extension options for a fee. The term should cover the build schedule plus a margin for delays and, if you plan to refinance, enough time to lease up or sell.
General information, not legal, tax or investment advice, and not an offer to lend. We match your deal to lenders. We are not a lender.